Methods for operating a combined cycle power plant and improving part load efficiency
Abstract:
A method for operating a combined cycle power plant (CCPP) and improving a part load operation of the CCPP is provided. The CCPP may include at least a gas turbine, a heat recovery steam generator (HRSG) located downstream of the gas turbine, a main steam turbine, and a supercritical steam turbine. The HRSG may include a low pressure steam system, an intermediate pressure steam system, and a high pressure steam system. To improve the part load efficiency of the CCPP, a base load operation of the CCPP may be initiated with supercritical pressure, via the supercritical steam turbine, such that the efficiency impact resulting from the part load operation is reduced.
Information query
Patent Agency Ranking
0/0