- Patent Title: Practical method for short-term operations of super large-scale hydropower plants
-
Application No.: US16644431Application Date: 2018-03-16
-
Publication No.: US11221594B2Publication Date: 2022-01-11
- Inventor: Jianjian Shen , Chuntian Cheng , Rui Cao , Qianqian Shen
- Applicant: DALIAN UNIVERSITY OF TECHNOLOGY
- Applicant Address: CN Liaoning
- Assignee: DALIAN UNIVERSITY OF TECHNOLOGY
- Current Assignee: DALIAN UNIVERSITY OF TECHNOLOGY
- Current Assignee Address: CN Liaoning
- Agency: Muncy, Geissler, Olds & Lowe, P.C.
- International Application: PCT/CN2018/079307 WO 20180316
- International Announcement: WO2019/174039 WO 20190919
- Main IPC: G05B13/04
- IPC: G05B13/04 ; H02J3/00 ; E02B9/00 ; G06F17/11

Abstract:
A practical method for short-term operations of large-scale hydropower plants divides all hydropower plants into three categories using operation characteristics such as system hierarchy, space attributes, task requirements, and schedule particularity. A strategy for adjusting spillage based on peak-shaving response and a strategy for equal load reduction in off-peak hours check and adjust power generation of hydropower plants with specified dispatching modes. For medium- and small-sized cascaded hydropower plants, the load distribution among plants is optimized with an objective of minimizing total power release subject to control condition of total generation profile. For large-size cascaded hydropower plants, an optimization model for peak-shaving operations and a method for balancing power plants with equal load rate are combined to respond to system peak demands and guarantee power balance in all periods.