Invention Grant
- Patent Title: Method for the installation of railway tracks on ballast, without an auxiliary track
- Patent Title (中): 在镇流器上安装铁路轨道的方法,无辅助轨道
-
Application No.: US12819682Application Date: 2010-06-21
-
Publication No.: US08397642B2Publication Date: 2013-03-19
- Inventor: Francisco Javier Miguelez Tapia
- Applicant: Francisco Javier Miguelez Tapia
- Applicant Address: ES Madrid
- Assignee: FCC Constructions, S.A.
- Current Assignee: FCC Constructions, S.A.
- Current Assignee Address: ES Madrid
- Agency: Sturm & Fix LLP
- Priority: ES200901480 20090623
- Main IPC: E01B29/05
- IPC: E01B29/05

Abstract:
A method for installing railway tracks onto ballast beds avoiding the need for installing any type of auxiliary track. The method comprises successive stages to be carried out after having located the sleepers onto the ballast bed, consisting of fixing and laying of a pair of rails from a mini train, for the transport of the rails with the fastening and traction of same up to their complete unloading, the operation being guided by means of a discharge wagon; supporting the rails on rollers for the longitudinal movement thereof; cutting, squaring and fixing the adjacent ends to the consecutive rails; raising the rail with the help of a crane, and removing the rollers; partial fastening of the track and placement of the rollers for the next cycle, and removing the tractor from the mini train, and the final fastening of the rails.
Public/Granted literature
- US20100320280A1 Method for the Installation of Railway Tracks on Ballast, Without an Auxiliary Track Public/Granted day:2010-12-23