Invention Grant
US09157193B2 Method for the installation of slab tracks in twin tube tunnels 有权
在双管隧道中安装平板轨道的方法

Method for the installation of slab tracks in twin tube tunnels
Abstract:
A method is described for the installation of slab tracks in tunnels, in particular tracks on a slab of concrete, with the optimized design and execution characteristics, and substantially increased performance compared to the normal known methods. The method includes a succession of phases executed in order, with the help of an auxiliary track, Consisting of the design of the construction section, the construction of the railway yards, assembly of the auxiliary track from the evacuation platform, execution of the foundation base, assembly of the track in slabs, transitions from slab track—ballast track, and placement of long bars and welding.
Public/Granted literature
Information query
Patent Agency Ranking