Method for shortening operation shutdown time of high pressure acid leach equipment in a hydrometallurgical process
Abstract:
This invention provides a method for shortening operation shutdown time of high pressure acid leach equipment in a hydrometallurgical process, wherein the high pressure acid leach equipment comprises (i) means to transfer an ore slurry into the high pressure acid leach equipment;(ii) means to increase temperature and pressure of an ore slurry before leaching; (iii) means to add sulfuric acid into the high pressure acid leach equipment and to leach the ore slurry to obtain a leached slurry at high temperature under high pressure; (iv) means to adjust the pressure of the leached slurry; and (v) means to discharge the leached from the high pressure acid leach equipment; wherein, upon operation shutdown of the high pressure acid leach equipment, the leached slurry is subjected to self-circulation inside the high pressure acid leach equipment.