교량 상부 구조물의 인상방법 및 구조
    11.
    发明公开
    교량 상부 구조물의 인상방법 및 구조 有权
    桥梁上部结构的打桩方法与结构

    公开(公告)号:KR1020030085620A

    公开(公告)日:2003-11-07

    申请号:KR1020020023488

    申请日:2002-04-29

    Applicant: 박재만

    Inventor: 박재만 홍순호

    Abstract: PURPOSE: A jacking method for an upper structure of a bridge is provided to prevent the fall, distortion and crack of a bridge when jacking the upper structure of a bridge. CONSTITUTION: The jacking method for an upper structure of a bridge comprises the steps of: interposing many hydraulic jacks(110¯130) on the lower part of a support beam(20) of a floor slab(10) and connecting hydraulic jacks(110¯130) and an oil pump(170) by a pipeline; installing a saddle bracket(200) coupled with a control rod(270) to the lower end of a support beam(20) of the floor slab(10) supported by the hydraulic jacks(110¯130); fixing a control rod guide bracket(300) to one side of a pier(30) to make the control rod(270) parallel to the side of the pier(30); fitting a control rod fixture(400) to the control rod(270) exposed to the lower end of the control rod guide bracket(300) and fixing the back end with a pin; and driving the oil pump(170) to make the compressed oil flow in through a pipeline, then lift up a support beam(20) of the floor slab(10).

    Abstract translation: 目的:提供一种桥梁上部结构的起重方法,以防止在桥梁上部结构抬起时桥梁的坠落,变形和破裂。 构成:桥梁上部结构的上升方法包括以下步骤:在楼板(10)的支撑梁(20)的下部插入许多液压千斤顶(110〜130),并连接液压千斤顶(110) 130)和油泵(170)通过管道; 将与控制杆(270)联接的鞍座(200)安装到由液压千斤顶(110〜130)支撑的地板(10)的支撑梁(20)的下端; 将控制杆引导支架(300)固定到墩(30)的一侧,以使控制杆(270)平行于码头(30)的一侧; 将控制杆固定装置(400)装配到暴露于控制杆引导支架(300)的下端的控制杆(270)上,并用销固定后端; 并且驱动油泵(170)使压缩油通过管道流入,然后提升楼板(10)的支撑梁(20)。

    12.
    外观设计
    失效

    公开(公告)号:KR3003271540000S

    公开(公告)日:2003-06-26

    申请号:KR3020020028246

    申请日:2002-09-28

    Applicant: 박재만

    Designer: 박재만

    교량 보수 보강장치 및 그 공법
    13.
    发明授权
    교량 보수 보강장치 및 그 공법 有权
    교량보수보강장치및그공법

    公开(公告)号:KR100388078B1

    公开(公告)日:2003-06-25

    申请号:KR1019990064768

    申请日:1999-12-29

    Inventor: 박재만

    Abstract: PURPOSE: A bridge repair and reinforcement method is provided to reduce bad influence against the safety of a structure, to construct safely, to prevent the damage of a beam caused by shearing, and to reduce maintenance costs caused by additional repair and reinforcement works. CONSTITUTION: A bridge repair and reinforcement method comprises the steps of installing a square anchoring jacket(200) to both ends of a PC(Pre-Cast) beam(100) in the form of covering the PC beam, fixing a fixture(400) to fix the end of a PC steel wire(500) to a fixing bracket(210) equipped to the square anchoring jacket, straining both ends of the PC steel wire, whose middle is placed over several steel middle saddles installed to the middle bottom of the PC beam and both ends are fixed to the fixture, by a tension gear connected to the fixture of the fixing bracket and re-straining the PC beam.

    Abstract translation: 目的:提供一种桥梁修补和加固方法,以减少对结构安全的不利影响,安全施工,防止由于剪切造成的梁的损坏,并减少由于额外的修理和加固工程造成的维护成本。 构成:桥梁修补和加固方法包括以下步骤:以覆盖PC梁的形式在PC(预制)梁(100)的两端安装方形锚固护套(200),固定夹具(400) 将PC钢丝(500)的端部固定在方形锚固套上的固定支架(210)上,将PC钢丝的两端拉紧,其中间放置在安装在中间底部的多个钢制中间鞍座上 PC梁和两端通过与固定支架的固定装置连接的张紧齿轮固定在夹具上,并重新张紧PC梁。

    합성 정착보강부를 이용한 강판형교의 강선 보강공법 및그 장치
    14.
    发明授权
    합성 정착보강부를 이용한 강판형교의 강선 보강공법 및그 장치 失效
    합성정착보강부를이용한강판형교교의강선보강공법법그장치

    公开(公告)号:KR100373522B1

    公开(公告)日:2003-03-03

    申请号:KR1020000046153

    申请日:2000-08-09

    Applicant: 박재만

    Inventor: 박재만

    Abstract: PURPOSE: A steel wire reinforcing method of a steel plate girder bridge using a composite anchorage-reinforcement part is provided to prevent buckle without damaging a steel plate girder, to reinforce by re-tensioning and to prevent damage caused by corrosion. CONSTITUTION: A steel wire reinforcing method of a steel plate girder bridge using a composite anchorage-reinforcement part comprises the steps of installing an iron frame(110) on both ends of a steel girder plate(10) of a steel plate girder bridge, forming a special concrete layer(120) to the inside of the iron frame(110), fixing an anchor bracket(130) to the outside of the iron frame(110) and the special concrete layer(120) by a high tensile bolt(150), fixing a gusset plate to both sides of the steel girder plate(10), forming a special concrete layer(120) to the lower part of the gusset plate, fixing primary and secondary saddles to the special concrete layer(120) by using the high tensile bolt(150), hanging a steel wire(W) on the primary and secondary saddles and connecting both ends of the steel wire(W) to an anchorage(400) coupled to an anchorage bearing part(140) of the anchor bracket(130), then tensioning and fixing.

    Abstract translation: 目的:提供一种采用复合锚固加固部件的钢板梁桥的钢丝加固方法,以防止扣损而不损坏钢板梁,通过再张紧来加固并防止腐蚀造成的损坏。 一种钢板梁桥的钢丝加固方法,其特征在于,在钢板梁桥的钢梁板(10)的两端安装铁框(110),成形 (110)内部的特殊混凝土层(120),通过高强度螺栓(150)将锚固托架(130)固定到铁框架(110)和特殊混凝土层(120)的外侧 ),将角撑板固定到钢梁板(10)的两侧,在角撑板的下部形成专用混凝土层(120),通过使用第一和第二鞍座将特殊混凝土层(120)固定到特殊混凝土层 所述高拉力螺栓150在所述主鞍座和所述辅鞍座上悬挂钢丝W并将所述钢丝W的两端连接到与所述锚固件的锚固支承部件140连接的锚固件400上, 支架(130),然后张紧和固定。

    역방향 가설 브래키트를 이용한 교량빔의 인상장치 및 그방법
    15.
    发明授权
    역방향 가설 브래키트를 이용한 교량빔의 인상장치 및 그방법 有权
    装置桥梁使用相对方向的临时构造支架及其方法

    公开(公告)号:KR100348632B1

    公开(公告)日:2002-08-22

    申请号:KR1019990066227

    申请日:1999-12-30

    Applicant: 박재만

    Inventor: 박재만

    Abstract: 본발명은교량의 PC빔의단부하측에결합되어상방향으로받쳐주는ㄷ자형빔하부받침형가설브래키트와, 상기빔하부받침형가설브래키트의측면에구비된걸림부의하부에결합되어상기빔하부받침형가설브래키트를상방향으로받쳐주는지지빔과, 상기지지빔과교각의상면사이에설치되어 PC빔을인상하는인상수단으로이루어진빔하부받침형역방향가설브래키트를이용한교량빔의인상장치와, 이를이용한역방향가설브래키트를이용한교량빔의인상방법을제공하고있다. 이러한본 발명은기존교량구조물에손상을주지않고교량의인상이가능하여구조물의안정성과장수명화에기여하는이점이있고, 이동및 설치가용이하도록 3개부분으로분리제작되어현장에서조립설치되는빔하부받침형가설브래키트를이용하여시공성이용이할뿐 아니라, 작업을안전하게행할수 있는이점이있으며, 각종교량에이미제작된빔하부받침형가설브래키트를조립하여인상잭킹공법을신속하게적용할수 있는이점이있고, 작업성을고려한빔 종단부의설치위치를적용하여작업시지장을주지않아작업성이향상되는이점이있다.

    교량의 부모멘트 방지장치 및 그 공법
    16.
    发明公开
    교량의 부모멘트 방지장치 및 그 공법 无效
    桥梁负荷预防装置及其构造方法

    公开(公告)号:KR1020010064555A

    公开(公告)日:2001-07-09

    申请号:KR1019990064770

    申请日:1999-12-29

    Inventor: 박재만

    Abstract: PURPOSE: A negative moment preventive device of a bridge and the construction method are provided to secure the safety of a structure by installing a negative moment preventive device to a joint of long span slabs, to reduce the damage of a bridge and to enlarge durability when external pressure such as an earthquake is applied. CONSTITUTION: A negative moment preventive device of a bridge comprises a steel wire tensioner(220) fixed to both adjacent ends of a PC beam(110) coupled to the top of a pier(100) and a PC steel wire(500') extended to the direction of pulling both ends of the PC beam by the steel wire tensioner; a bridge repair and reinforcement method comprises the steps of installing a fixing jacket(200) on both ends of the PC beam in the form of covering the PC beam, fixing a fixture to set the end of the PC steel wire to the middle of the PC beam, placing the PC steel wire over a negative moment preventive saddle(600) equipped to each fixing jacket and straining both ends of the PC steel wire by a tension gear coupled to the fixture.

    Abstract translation: 目的:提供一种桥梁的负矩预防装置及其施工方法,以便通过在长跨度板的接头上安装负力矩防止装置来确保结构的安全性,以减少桥梁的损坏并增加桥梁的耐久性 外部压力如地震。 构成:桥梁的负矩防止装置包括固定到耦合到墩(100)的顶部的PC梁(110)的两个相邻端的钢丝张紧器(220)和延伸的PC钢丝(500') 通过钢丝张紧器拉动PC梁的两端的方向; 桥梁修复和加固方法包括以PC梁的两端安装固定护套(200)的步骤,以PC梁的形式安装固定护套(200),固定夹具以将PC钢丝的末端设置在 PC梁,将PC钢丝绳放置在每个固定护套上的负力矩预防鞍座(600)上,并通过连接到固定装置的张力齿轮拉紧PC钢丝绳的两端。

    상부 구조물 인상을 위한 조립식 브래키트
    17.
    实用新型
    상부 구조물 인상을 위한 조립식 브래키트 失效
    用于提升上层建筑的预制托架

    公开(公告)号:KR200227911Y1

    公开(公告)日:2001-06-15

    申请号:KR2020000036386

    申请日:2000-12-26

    Applicant: 박재만

    Inventor: 박재만

    Abstract: 본 고안은 상부 구조물 인상을 위한 조립식 브래키트에 관한 것으로, 교량의 교각 및 교대의 코핑부와 같은 제1 대상물과 교각 위에 설치되는 PC빔 등의 주빔과 같은 제2 대상물의 사이에 유압잭과 같은 유압장치를 설치하여 제2 대상물을 인상하는 장치에 있어서, 상기 제1 대상물과 제2 대상물의 양측부에 결합되고 그들 사이의 중간부에 가로질러 고정되는 중간요소를 피하여 결합될 수 있도록 간섭방지홈이 구비되며, 상기 유압장치를 설치하기 위한 버팀부가 상기 제2 대상물의 외측으로 돌출되게 형성되는 한 쌍의 분할요소와, 상기 양쪽 분할요소를 결합되는 길이를 가변시켜 체결하기 위한 가변체결요소를 포함하여 구성된다. 이러한 본 고안은 교각과 교대의 코핑부 상단을 덮는 형태로 구조물 손상과 교통통제 없이 받침부에 조립, 설치하여 잭을 설치한 후 신속하고 안전하게 교량 상부 구조물을 인상할 수 있는 이점이 있다. 또, 버팀판을 추가 설정하여 단부판과의 충분한 용접길이를 확보할 수 있으므로 내하력이 증가되어 더 큰 잭킹력에 견딜 수 있는 이점이 있다. 또한, 형하공간 및 연단거리의 제약을 해소할 수 있는 이점이 있고, 연결판의 볼트 채움에 의하여 조립식 브래키트를 폭이 다른 교각에 재사용할 수 있는 이점이 있다. 그리고, 이동 및 실처가 용이하도록 2개 부분으로 제작되어 있으므로 시공성이 용이한 이점이 있다.

    합성 정착보강부를 이용한 강판형교의 강선 보강장치
    18.
    实用新型
    합성 정착보강부를 이용한 강판형교의 강선 보강장치 失效
    采用合成固定钢筋的钢丝增强钢板桥

    公开(公告)号:KR200208848Y1

    公开(公告)日:2001-01-15

    申请号:KR2020000022680

    申请日:2000-08-09

    Applicant: 박재만

    Inventor: 박재만

    Abstract: 본 고안은 합성 정착보강부를 이용한 강판형교의 강선 보강장치에 관한 것으로, 강판형교(steel plate girder bridge)의 강판보(steel plate girder)의 양단부에 철재골조를 형성하고, 특수콘크리트층을 타설하여 양생시키며, 그 외측으로 정착구 지지부가 구비된 정착 브래키트를 결합하고, 강판보의 중간부에는 복수개의 새들을 결합한 후, 상기 정착 브래키트의 정착구 지지부에 결합되는 정착구와 새들에 강연선을 걸치고 긴장시켜 내하력을 증강시키는 장치이다. 이러한 본 고안은 종래에는 프리스트레스 공법을 적용할 때에 강판보의 단부를 훼손시키지 않고는 주형을 보강할 수 없다는 문제점을 개선하기 위하여 개발된 것으로 단지간과 합성구간 두가지 모두에 사용 가능하며, 강판보를 손상시키지 않고 좌굴을 방지하면서 재긴장시켜 보강할 수 있는 이점이 있고, 부식에 의한 손상을 방지할 수 있는 이점 등이 있다.

    콘크리트 구조물 보수용 인상장치
    19.
    实用新型
    콘크리트 구조물 보수용 인상장치 失效
    推进装备修复混凝土结构

    公开(公告)号:KR200186827Y1

    公开(公告)日:2000-06-15

    申请号:KR2019990027471

    申请日:1999-12-08

    Applicant: 박재만

    Inventor: 박재만

    CPC classification number: B66F3/25 B66F3/30 E01D22/00

    Abstract: 본 고안은 콘크리트 구조물 보수용 인상장치에 관한 것으로, 유압잭의 실린더에 상승되어진 플런저가 하강하지 못하도록 로크시키기 위한 로킹수단과, 상기 플런저에 의해 인상된 인상 대상물의 인상된 높이를 측정하기 위한 측정수단을 포함하여 구성되고, 상기 플런저의 상부에 2단 접촉구를 높이조절수단에 의해 높이 조절 가능하게 결합하여 구성된다.
    이러한 본 고안은 유압잭의 플런저 상부에 2단 접촉구를 높이조절수단에 의해 높이 조절 가능하게 구성되어 있으므로 인상 대상물과 지지요소사이의 거리가 상이한 경우에 다양하게 설치하여 편리하게 보수, 보강공사를 행할 수 있는 이점이 있다. 또, 플런저 조립체를 인상시킨 후, 로킹수단의 잠금구로 플런저가 하강하지 못하도록 로킹함으로써 인상된 인상 대상물을 안정하게 유지할 수 있는 이점이 있으며, 이에 따라 인상 후 행하는 보수, 보강공사를 안전하고 간편하게 행할 수 있는 이점이 있다. 또한, 인상잭의 상단부에 합성교좌장치를 설치하여 교량 보수, 보강공사를 위한 인상작업시 교좌장치의 공백으로 인한 교량의 파손을 방지하는 이점이 있다.

    Abstract translation: 目的:提供一种用于修复混凝土结构的升降装置,以通过使用高度调节器来控制升高的高度,并通过使用锁定部件将柱塞锁定在升高的状态。 构成:为了提升物体(O),例如PC梁,油液装置安装在物体的两端和支撑元件(S)之间。 旋转高度调节器(15)的插座(16),以将两步接触器(14)的粘合板(14A)附接到物体的下表面上。 油压提升装置连接到油压泵,用于通过软管(6A)将抽油机液压油喷射到每个油压提升装置中的气缸(1)的油压端口(1A)上。 气缸的油压室中的压力增大,用于升高包括柱塞主体(3)和两级接触器的柱塞组件(P)。 因此,物体被升高,并且锁定部件(10)的储物柜(9)旋转以将上端附接到一步接触器(5)的粘合板(5A)上。 因此,防止接触器降低,并且防止柱塞组件降低以保持物体的升高状态。

    프리스트레스 구조물의 재긴장장치
    20.
    实用新型
    프리스트레스 구조물의 재긴장장치 失效
    限制预约结构的装置

    公开(公告)号:KR200182611Y1

    公开(公告)日:2000-05-15

    申请号:KR2019990027470

    申请日:1999-12-08

    Applicant: 박재만

    Inventor: 박재만

    Abstract: 본 고안은 PC빔의 양단부에 고정되는 정착구의 후방에 결합되고 PC강연선을 고정하기 위한 적어도 하나 이상의 콜렛이 결합되어진 헤드에 연결되는 연결결합요소와, 상기 연결결합요소를 후방으로 당겨주기 위한 긴장수단과, 상기 긴장수단에 의해 상기 연결결합요소가 당겨져 상기 PC강연선이 인장된 후 상기 정착구의 고정판과 헤드 사이에 삽입하여 상기 PC강연선 및 헤드의 복귀를 저지함으로써 인장된 형태를 유지하기 위한 간격유지구를 포함하여 구성된다.
    이러한 본 고안은 정착구의 헤드 외측으로 PC강연선이 짧게 노출된 경우에도 연결결합요소로 연장시켜 인장잭으로 긴장시킬 수 있으므로, 교량빔의 처짐을 PC강연선의 돌출된 길이에 구애됨이 없이 폭넓게 보강할 수 있는 이점이 있다. 따라서, 본 고안은 종래 기술에 비하여 교량빔의 처짐을 보정하는 데 따른 소요공기를 단축하고 공비를 현저히 절감할 수 있으며 보다 효율적인 보정이 가능하게 될 뿐만 아니라, 특히 재긴장작업을 폭넓게 적용하여 적기의 보정이 가능하게 됨으로써 교량빔을 포함하는 상부 구조물 즉, 전체 교량의 안정성을 적기에 확보할 수 있는 효과가 있다.