계통 구성 판별 장치 및 방법
    51.
    发明公开
    계통 구성 판별 장치 및 방법 审中-实审
    用于辨别电力系统配置的装置和方法

    公开(公告)号:KR1020160044919A

    公开(公告)日:2016-04-26

    申请号:KR1020140140020

    申请日:2014-10-16

    CPC classification number: H02J3/00 H02J2003/001 H02J2003/007

    Abstract: 본발명은모선분리나편단개방구성선로등의예외적인계통구성에대한병행 2회선에대한상정고장을모의할수 있는계통구성판별장치및 방법에관한것이다. 이를위한본 발명의계통구성판별장치는모선분리또는편단개방에의해파생된부모모선및 자녀모선각각에대한부모모선번호및 자녀모선번호를포함하는모선정보를생성하는모선정보생성부; 부모모선번호와자녀모선번호를하나의통합모선번호로변환하고, 통합모선번호를등가모선번호로변환함으로써등가모선정보를생성하는등가변환부; 및등가모선정보를근거로상정고장리스트정보를출력하는상정고장탐색부를포함하고, 상정고장리스트정보는상정고장모의에이용되는모선들의모의순서, 설비정보및 등가모선정보중 적어도하나를포함할수 있다.

    Abstract translation: 本发明涉及一种用于区分电力系统配置的装置和方法,其能够模拟平行双回路传输线的偶然性,例如诸如母线分离或一端开放配置之类的例外系统配置 传输线。 为此,根据本发明的用于区分电力系统配置的装置包括:汇流条信息产生部分,用于产生母线信息,母线数目和母线母线数目相对于父母线 和一个由母线分离或一端开放产生的儿童母线; 用于将母线母线数和子母线数转换为一个联合母线条的等效转换部分,以及通过将联合母线条编号转换为等效总线条编号来产生等效母线信息; 以及应急调查部,其基于所述等效母线信息输出所述意外事件的列表信息,其中,所述意外事件的列表信息包括以下中的至少一个:模拟命令,设施信息和所使用的母线的等效母线信息 偶然性的模拟。

    전력 계통의 전압 안정도 관리 장치 및 그 방법
    52.
    发明公开
    전력 계통의 전압 안정도 관리 장치 및 그 방법 有权
    用于管理电力系统电压稳定性的装置和方法

    公开(公告)号:KR1020160028751A

    公开(公告)日:2016-03-14

    申请号:KR1020140117674

    申请日:2014-09-04

    CPC classification number: H02J3/16 H02J3/24 H02P9/105 Y02E40/34

    Abstract: 본발명은전력계통의전압안정도관리장치및 그방법에관한것으로, 다수개의대상모선으로부터수신한전압정보를이용하여무효전력출력비율정보를생성하는속응형전압제어부; 생성된무효전력출력비율정보를토대로무효전력기준정보를생성하고, 생성된무효전력기준정보를이용하여단자전압조정정보를생성하는무효전력분배부; 생성된단자전압조정정보를이용하여단자전압을조정하는단자전압조정부; 주파수변동시 보조신호를발생시켜상기무효전력분배부에제공하는과도저감제어부; 및대상모선의전압을측정하여보조신호를발생시켜상기단자전압조정부에제공하는전압조정제어부;를포함한다.

    Abstract translation: 本发明涉及一种用于管理电力系统中的电压的稳定性的装置和方法。 该装置包括:快速自适应电压控制单元,用于通过使用从多个目标总线接收的电压信息来产生无功功率输出比信息; 无功功率分配单元,用于基于所生成的无功功率输出比信息生成无功功率参考信息,并且通过使用所生成的无功功率参考信息来生成终端电压调整信息; 端子电压调整单元,用于通过使用所生成的端子电压调整信息来调节端子电压; 过电压降低控制单元,用于当频率改变时产生辅助信号,并将产生的辅助信号提供给无功功率分配单元; 以及电压调节控制单元,用于通过测量目标总线的电压来产生辅助信号,并将产生的辅助信号提供给端子电压调节单元。

    고장전류의 기여도 평가 장치 및 그 방법
    53.
    发明公开
    고장전류의 기여도 평가 장치 및 그 방법 审中-实审
    用于评估故障电流的贡献率的方法及其方法

    公开(公告)号:KR1020160024024A

    公开(公告)日:2016-03-04

    申请号:KR1020140109468

    申请日:2014-08-22

    Abstract: 본발명은고장전류의기여도평가장치에관한것으로, 전력계통을구성하는복수의발전기, 복수의무효전력보상장치및 송변전설비의구성과연결에관한정보를입력받는입력부, 복수의발전기및 복수의무효전력보상장치중 평가대상이되는고장전류발생원과고장지점을설정하고, 복수의발전기에대응되는단자전압의크기와위상, 및복수의무효전력보상장치에대응되는투입용량을설정하는설정부, 설정부를통해설정된고장지점으로유입되는, 고장전류발생원각각으로인한유입전류를산출하는분석부및 분석부를통해산출된유입전류에기초하여고장지점에대한고장전류발생원각각으로인한고장전류의기여도를평가하는평가부를포함한다.

    Abstract translation: 本发明涉及一种用于评估故障电流的贡献度的装置。 用于评估故障电流的贡献度的装置包括:输入单元,其接收关于构成电力的多个发电机,多个无功功率补偿器和电力传输和变换设备的配置和连接的信息 系统; 设置单元,其将所述故障电流产生源和故障点设置为所述多个发电机和所述多个无功功率补偿器中的评估对象,并且设定与所述多个发电机对应的端子电压的大小和相位, 对应于多个无功功率补偿器的容量; 分析单元,其计算由每个故障电流发生源引起的流入电流,流入通过设定单元设定的故障点的流入电流; 以及评估单元,其基于通过所述分析单元计算的流入电流来评估由所述故障电流产生源中的每一个相对于所述故障点引起的故障电流的贡献度。

    전력 계통의 부하 제어 장치 및 방법
    54.
    发明公开
    전력 계통의 부하 제어 장치 및 방법 审中-实审
    用于控制电力系统负载的装置和方法

    公开(公告)号:KR1020150037292A

    公开(公告)日:2015-04-08

    申请号:KR1020130116798

    申请日:2013-09-30

    Abstract: 전력계통의상정고장발생시안정도를회복하기위하여부하를차단함에있어서실시간차단되는발전기에대한정보를입수하여, 차단하려는부하량을정확하게산출하는전력계통의부하제어장치및 방법이개시된다. 본발명에따른전력계통의부하제어장치는, 시각동기화가지원되는 SCADA/EMS로부터실시간전력계통데이터를수집하는데이터수집부, 상기데이터수집부에서수집된전력데이터를이용하여상기전력계통의상정고장발생시발전기의차단여부및 상기발전기의차단대수에대한정보인발전기차단정보를생성하는발전기차단정보생성부및 상기전력데이터및 발전기차단정보를기반으로상기상정고장발생시차단하는부하량에대한정보인부하차단정보를생성하는부하차단정보생성부를포함한다.

    Abstract translation: 公开了一种用于控制电力系统的负载的装置和方法,其能够通过获取关于在电力系统中发生应急事件时中断负载以恢复稳定性的实时中断的发电机的信息来精确地计算要中断的负载的量 。 根据本发明的用于控制电力系统的负载的装置包括:数据收集单元,用于从支持时间同步的SCADA / EMS收集实时电力系统数据; 发电机中断信息生成单元,通过使用由所述数据收集单元收集的电力数据,生成关于发电机是否中断的信息,或者在电力系统中发生意外事件时中断的发电机的数量的发电机中断信息; 以及负载中断信息生成单元,其基于所述功率数据和所述发电机中断信息,生成负载中断信息,所述负载中断信息是关于所述事件发生时中断的负载量的信息。

    부하 제어 장치 및 방법
    55.
    发明公开
    부하 제어 장치 및 방법 无效
    负载控制装置和方法

    公开(公告)号:KR1020140040405A

    公开(公告)日:2014-04-03

    申请号:KR1020120106985

    申请日:2012-09-26

    CPC classification number: Y02B70/3225 Y04S20/222

    Abstract: An apparatus and a method for controlling a load are disclosed. The apparatus for controlling a load comprises four main components: a data acquisition/processing unit which acquires power system data, and time synchronization data corresponding to the power system data from a Supervisory Control And Data Acquisition (SCADA) system, and a time synchronization measuring device, respectively, and generates tidal current calculation data by using the power system data and time synchronization data; a data analysis unit which calculates a power generation complexity cost according to an available power limit of the power system by using the tidal current calculation data, and analyzes an economic feasibility related to loss costs due to a disconnection of a load to calculate an optimal load disconnection amount; a disconnection distribution line selecting unit which selects a distribution line to be disconnected based on the optimal load disconnection amount; and a load disconnecting unit which transmits a disconnection signal to the selected distribution line. [Reference numerals] (10) SCADA system; (110) Data acquisition/processing unit; (120) Data analysis unit; (121) Power system analysis unit; (122) Economic feasibility analysis unit; (130) disconnection distribution line selecting unit; (140) Load disconnecting unit; (20) Time synchronization measuring device

    Abstract translation: 公开了一种用于控制负载的装置和方法。 用于控制负载的装置包括四个主要部件:获取电力系统数据的数据采集/处理单元,以及来自监控和数据采集(SCADA)系统的与电力系统数据相对应的时间同步数据,以及时间同步测量 并通过使用电力系统数据和时间同步数据产生潮汐流计算数据; 数据分析单元,其通过使用潮汐流计算数据根据电力系统的可用功率限制来计算发电复杂度成本,并且分析与由于负载断开而导致的损失成本相关的经济可行性,以计算最佳负载 断线量; 断线分配线选择单元,其基于最佳负载断开量选择要断开的配线; 以及将断开信号发送到所选分配线路的负载断开单元。 (附图标记)(10)SCADA系统; (110)数据采集/处理单元; (120)数据分析单元; (121)电力系统分析单元; (122)经济可行性分析单位; (130)断线配线选择单元; (140)负载断路装置; (20)时间同步测量装置

    전력계통 광역정전 복구 장치 및 그 방법
    56.
    发明公开
    전력계통 광역정전 복구 장치 및 그 방법 无效
    电力系统故障恢复系统及方法

    公开(公告)号:KR1020140039879A

    公开(公告)日:2014-04-02

    申请号:KR1020120106670

    申请日:2012-09-25

    CPC classification number: H02J9/04 Y04S10/265 Y04S10/525

    Abstract: The present invention relates to a system and method for reconstructing a wide area power outage in an electric power system, which includes: a data acquiring unit for acquiring information data in the electric power system having phase information from monitoring devices in the electric power system; a data analyzing unit for analyzing the information data therein to determine whether power outage occurs and determine the range of which the power outage occurs; and an establishing unit of power outage reconstructing procedure for establishing a power outage reconstructing procedure by checking whether an operating generator is mounted and an interconnection tie path in an external area is able to be connected within the range thereof as a determined result. [Reference numerals] (10) Remote monitoring control unit; (110) Data acquiring unit; (120) Data analyzing unit; (130) Power outage reconstructing procedure establishing unit; (140) Procedure performing mode selecting unit; (145) Information display unit; (150) Operational control unit; (20) Phase measurement unit

    Abstract translation: 本发明涉及一种用于重建电力系统中的广域停电的系统和方法,包括:数据获取单元,用于从电力系统中的监控装置获取具有相位信息的电力系统中的信息数据; 数据分析单元,用于分析其中​​的信息数据,以确定是否发生停电,并确定发生停电的范围; 以及用于通过检查是否安装了操作发电机并且在外部区域中的互连连接路径能够在其范围内连接作为确定结果来建立停电重建过程的停电重建过程的建立单元。 (附图标记)(10)远程监控控制单元; (110)数据采集单元; (120)数据分析单元; (130)断电重建程序建立单位; (140)程序执行模式选择单元; (145)信息显示单元; (150)操作控制单元; (20)相位测量单元

    발전 시스템 및 전력계통 안정화 장치의 성능 시험 방법
    57.
    发明授权
    발전 시스템 및 전력계통 안정화 장치의 성능 시험 방법 有权
    电力分配系统和稳定电力系统设备的测试方法

    公开(公告)号:KR101073088B1

    公开(公告)日:2011-10-12

    申请号:KR1020090093561

    申请日:2009-09-30

    Abstract: 발전시스템이개시된다. 발전시스템은발전기의출력전압과전력계통의무효전력을제어하는자동전압조정장치및 상기자동전압조정장치와연결되어상기전력계통의유효전력을조정하고, 상기전력계통의전력흐름을안정시키는전력계통안정화장치를포함하되, 상기자동전압조정장치는상기전력계통안정화장치의동작성능을시험하는안정화시험부를포함할수 있다.

    발전 시스템 및 전력계통 안정화 장치의 성능 시험 방법
    58.
    发明公开
    발전 시스템 및 전력계통 안정화 장치의 성능 시험 방법 有权
    电力分配系统和稳定电力系统设备的测试方法

    公开(公告)号:KR1020110035732A

    公开(公告)日:2011-04-06

    申请号:KR1020090093561

    申请日:2009-09-30

    Abstract: PURPOSE: A performance test method of a power system stabilizer is provide to check the driving property of the power system stabilizer in the real situation. CONSTITUTION: An automatic voltage control device(100) controls the output voltage of a power generator and a reactive power of the electric power system. The automatic voltage control device comprises a stabilization test part for testing the performance capacity of the power system stabilizer. The automatic voltage control device comprises a controller(110) which processes the input and the output signal in order to control the power generator. A power system stabilizer adjusts the active power of the electric power system.

    Abstract translation: 目的:提供电力系统稳定器的性能测试方法,以便在实际情况下检查电力系统稳定器的驾驶特性。 构成:自动电压控制装置(100)控制发电机的输出电压和电力系统的无功功率。 自动电压控制装置包括用于测试电力系统稳定器的性能能力的稳定测试部件。 该自动电压控制装置包括控制器(110),该控制器处理输入和输出信号以便控制发电机。 电力系统稳定器调整电力系统的有功功率。

    신규 발전소의 건설공기 단축 및 지연에 대한 경제성 분석 시스템
    59.
    发明公开
    신규 발전소의 건설공기 단축 및 지연에 대한 경제성 분석 시스템 无效
    评估新发电厂建设时间表变更经济效益​​的制度

    公开(公告)号:KR1020110029399A

    公开(公告)日:2011-03-23

    申请号:KR1020090087056

    申请日:2009-09-15

    CPC classification number: G06Q50/08 G06Q50/06

    Abstract: PURPOSE: A system for assessing the economical efficiency of construction schedule change of a new power plant is provided to enable decision makers to make objective decision by analyzing the economical efficiency on the change of the construction schedule. CONSTITUTION: An economic efficiency analysis module(20) comprises followings. If the construction schedule change is needed, a manpower re-calculation module(20a) calculates the needed manpower again corresponding to the changed construction schedule. A construction cost re-calculation module(20b) performs an adjustment of the construction costs coping with the changed construction schedule. A construction interest re-calculation module(20c) estimates construction interest based on the re-calculated construction costs.

    Abstract translation: 目的:提出一个评估新发电厂施工进度变化经济效益的系统,使决策者能够通过分析施工进度变化的经济效益来做出客观决定。 规定:经济效益分析模块(20)包括以下内容。 如果需要施工进度更改,则人力重计算模块(20a)根据改变的施工进度再次计算需要的人力。 施工成本重新计算模块(20b)根据改变的施工进度对施工成本进行调整。 建设利息重估模块(20c)根据重新计算的建筑成本估算建设利息。

    대표 모선 선정 방법
    60.
    发明公开
    대표 모선 선정 방법 有权
    选择电力系统中的导线总线的方法

    公开(公告)号:KR1020090032597A

    公开(公告)日:2009-04-01

    申请号:KR1020070097964

    申请日:2007-09-28

    Abstract: A method for selecting a pilot bus with a sensitivity matrix is provided to improve a voltage stability of a power system by stably controlling a pilot bus voltage into a secondary voltage control method. A method for selecting a pilot bus with a sensitivity matrix comprises the following steps: a step for calculating a susceptance matrix about a bus of a power system(S100); a step for calculating a sensitivity matrix from a reverse matrix of the susceptance matrix(S110); a step for arranging the sensitivity matrix according to a size of a diagonal component of the sensitivity matrix(S120); a step for comparing a bus positioned in a smallest diagonal component among the diagonal component of the sensitivity matrix with a limited condition of the pilot bus(S130); and a step for selecting a bus corresponding to the smallest diagonal component among the diagonal component of the sensitivity matrix as a pilot bus(S150).

    Abstract translation: 提供一种用于选择具有灵敏度矩阵的先导总线的方法,通过将先导总线电压稳定地控制到次级电压控制方法来提高电力系统的电压稳定性。 一种用于选择具有灵敏度矩阵的导频总线的方法包括以下步骤:用于计算关于电力系统总线的电纳矩阵的步骤(S100); 从所述电纳矩阵的反矩阵计算灵敏度矩阵的步骤(S110); 根据灵敏度矩阵的对角线分量的大小布置灵敏度矩阵的步骤(S120); 用于将位于所述灵敏度矩阵的对角分量中的最小对角分量中的总线与所述导频总线的有限条件进行比较的步骤(S130); 以及用于选择对应于灵敏度矩阵的对角分量中的最小对角线分量的总线作为导频总线的步骤(S150)。