Method and system for assessing the progress of a project in terms of its schedule
    1.
    发明授权
    Method and system for assessing the progress of a project in terms of its schedule 有权
    方案和制度,用于评估项目进度情况

    公开(公告)号:US08452634B2

    公开(公告)日:2013-05-28

    申请号:US12788399

    申请日:2010-05-27

    CPC classification number: G06Q10/06 G06Q10/06313 G06Q10/0639

    Abstract: The invention describes a computer-implemented method and system for assessing the progress of a project in terms of its schedule. The method includes receiving project data and based on the project data, calculating a first period (PE) after which a current earned value (EV) was expected to be realized. The method also includes calculating a second period (PR) in which the current EV has been realized. Further, the method includes calculating a fraction component (EF) of a period when the current EV was expected to be realized and finally, calculating an earned schedule performance index (ESPI) based on PE, PR and EF, wherein the ESPI indicates whether the project is on schedule.

    Abstract translation: 本发明描述了一种计算机实现的方法和系统,用于根据其进度来评估项目的进度。 该方法包括接收项目数据,并根据项目数据,计算第一期(PE),之后预计实现当前所得值(EV)。 该方法还包括计算已经实现了当前EV的第二周期(PR)。 此外,该方法包括计算期望实现当前EV的时段的分数分量(EF),并且最终计算基于PE,PR和EF的获得的日程表性能指数(ESPI),其中ESPI指示是否 项目按计划进行。

    METHOD AND SYSTEM FOR ASSESSING THE PROGRESS OF A PROJECT IN TERMS OF ITS SCHEDULE
    2.
    发明申请
    METHOD AND SYSTEM FOR ASSESSING THE PROGRESS OF A PROJECT IN TERMS OF ITS SCHEDULE 有权
    评估项目进展情况的方法和系统

    公开(公告)号:US20110112883A1

    公开(公告)日:2011-05-12

    申请号:US12788399

    申请日:2010-05-27

    CPC classification number: G06Q10/06 G06Q10/06313 G06Q10/0639

    Abstract: The invention describes a computer-implemented method and system for assessing the progress of a project in terms of its schedule. The method includes receiving project data and based on the project data, calculating a first period (PE) after which a current earned value (EV) was expected to be realized. The method also includes calculating a second period (PR) in which the current EV has been realized. Further, the method includes calculating a fraction component (EF) of a period when the current EV was expected to be realized and finally, calculating an earned schedule performance index (ESPI) based on PE, PR and EF, wherein the ESPI indicates whether the project is on schedule.

    Abstract translation: 本发明描述了一种计算机实现的方法和系统,用于根据其进度来评估项目的进度。 该方法包括接收项目数据,并根据项目数据,计算第一期(PE),之后预计实现当前所得值(EV)。 该方法还包括计算已经实现了当前EV的第二周期(PR)。 此外,该方法包括计算期望实现当前EV的时段的分数分量(EF),并且最终计算基于PE,PR和EF的获得的日程表性能指数(ESPI),其中ESPI指示是否 项目按计划进行。