公开(公告)号:KR1020090001292A
公开(公告)日:2009-01-08
申请号:KR1020070065555
申请日:2007-06-29
Applicant: 광운대학교 산학협력단 , 재단법인서울대학교산학협력재단
CPC classification number: G06Q10/0639 , G06Q10/10
Abstract: A network-base operation performance analysis system for analyzing reliability of an operation plan and an index and method for the same are provided to collect information about daily operation plan from construction project participants connected to a wire and wireless network. A network-base operation performance analysis system for analyzing reliability of an operation plan and an index comprises a step of requesting a participant terminal authenticated by an operator server to fill out a daily operation planning query form, a step of transmitting the daily operation planning indication form reflecting an examination opinion of a process manager based on daily operation planning information which is input by the participant terminal, a step of analyzing a result of work about an knowledge task by using a analysis module based on the daily operation planning information and a step of transmitting a result, processed in the operator server, to the participant terminal.
Abstract translation: 提供用于分析操作计划的可靠性的网络操作性能分析系统及其索引和方法,以从连接到有线和无线网络的建筑项目参与者收集关于日常操作计划的信息。 一种用于分析操作计划和索引的可靠性的网络操作性能分析系统,包括:请求由操作员服务器认证的参与者终端填写日常操作规划查询表单的步骤;发送日常操作规划指示 基于由参与者终端输入的日常运营规划信息反映过程管理者的考察意见的形式,通过使用基于日常运营规划信息的分析模块分析知识任务的工作结果的步骤,以及步骤 将在运营商服务器中处理的结果发送给参与者终端。
-
公开(公告)号:KR1020070077159A
公开(公告)日:2007-07-25
申请号:KR1020070062090
申请日:2007-06-25
Applicant: 광운대학교 산학협력단 , 재단법인서울대학교산학협력재단
CPC classification number: G06Q50/08 , G06Q10/06312 , H04W88/02
Abstract: A system and a method for managing a process are provided to solve delay of each work/manager in a construction project by checking the delay generated from each company, manager, and work group, and causes of the delay, and efficiently manage the process by rebuilding a work plan based on the checked delay and causes. A database server(110) classifies and stores manager information managing the construction project, the work plans, and work lists. Each manager terminal(120) is connected to the database server, and transmits a work result of each work field according to a daily work order form. An operator server(130) transmits the daily work order form according to the work plan to the manager terminals and calculates work reliability comparing work amount included in the daily work order form with the performed work amount. If the work reliability is not 100 percents, the operator server rebuilds the work plan by mapping the process and transmits the rebuilt work plan to the database server. The manager terminal is a PC, a PDA(Personal Digital Assistant), or a mobile terminal.
Abstract translation: 提供一种管理流程的系统和方法,通过检查每个公司,管理人员和工作组产生的延迟以及延迟的原因来解决建设项目中每个工作/经理的延误,并通过 根据检查的延迟和原因重建工作计划。 数据库服务器(110)对管理建设项目,工作计划和工作列表的管理信息进行分类和存储。 每个管理终端(120)连接到数据库服务器,并根据日常工作单发送每个工作字段的工作结果。 运营商服务器(130)根据工作计划向管理者终端发送日常工单,并计算作业可靠性,将包含在日常工单中的工作量与所执行的工作量进行比较。 如果工作可靠性不是百分之百,操作员服务器通过映射过程重建工作计划,并将重建的工作计划传送到数据库服务器。 经理终端是PC,PDA(个人数字助理)或移动终端。
-
公开(公告)号:KR1020090114241A
公开(公告)日:2009-11-03
申请号:KR1020080040081
申请日:2008-04-29
Applicant: 광운대학교 산학협력단 , 재단법인서울대학교산학협력재단
CPC classification number: G06Q10/087 , G06Q10/0637 , G06Q50/08
Abstract: PURPOSE: A system for analyzing resource supplying performance is provided to minimize a material containing amount inside a construction site and unnecessary material movement, thereby reducing material costs. CONSTITUTION: A material storage state input window through which a material storage state can be input and a material installation number input window through which a material installation number can be input are transmitted from a resource supply performance analyzing server(2). A distribution administrator terminal(6) transmits the material warehouse state and the material installation number to the resource supply performance analyzing server. A system administrator terminal(4) changes an expected material storage date and a material order by receiving distribution management information form the resource supply performance analyzing server.
Abstract translation: 目的:提供一种用于分析资源供应性能的系统,以最大限度地减少施工现场内的材料含量和不必要的材料运动,从而降低材料成本。 构成:从资源供给性能分析服务器(2)发送可以输入材料存储状态的材料存储状态输入窗口和可以输入材料安装号的材料安装号输入窗口。 配送管理员终端(6)将材料仓库状态和物料安装号码发送到资源供应绩效分析服务器。 系统管理员终端(4)通过从资源供应绩效分析服务器接收分发管理信息来改变期望的物料存储日期和物料订单。
-
公开(公告)号:KR1020090114242A
公开(公告)日:2009-11-03
申请号:KR1020080040082
申请日:2008-04-29
Applicant: 광운대학교 산학협력단 , 재단법인서울대학교산학협력재단
CPC classification number: Y02P90/30 , G06Q50/04 , G06Q10/109
Abstract: PURPOSE: A work condition analyzing system is provided to change a process project according to whether to perform a work, thereby preventing a work delay in advance. CONSTITUTION: A site administrator terminal(6) receives a work condition input window through work condition information can be inputted from a work condition analyzing server. The site administrator terminal provides work performance information to the work condition analyzing server. A system administrator terminal(4) modifies a weekly work list and a monthly work list according to a work condition included in works of the weekly work list and the monthly work list.
Abstract translation: 目的:提供工作条件分析系统,根据是否进行工作改变过程项目,从而预防工作延迟。 构成:站点管理员终端(6)通过工作条件信息接收工作条件输入窗口可以从工作条件分析服务器输入。 站点管理员终端向工作状态分析服务器提供工作性能信息。 系统管理员终端(4)根据每周工作列表和每月工作列表中的工作条件修改每周工作列表和每月工作列表。
-
公开(公告)号:KR1020100100217A
公开(公告)日:2010-09-15
申请号:KR1020090018976
申请日:2009-03-05
Applicant: 광운대학교 산학협력단 , 서울대학교산학협력단
CPC classification number: G06Q10/0639 , G06Q50/08
Abstract: PURPOSE: A performance evaluation system is provided to manage distribution information of necessary resources according to work planning after constructing work plan about construction project, thereby preventing the demage of materials. CONSTITUTION: An operator server(10) processes user authentication about a participant terminal(40). The operator server analyzes the resource supplying performance through distribution information provided by the participant terminal. The operator server stores the analyzed resource supply performance information to a DB server(20). The operation server analyzes work performance by calculating reliability, usefulness, efficiency of relevant work.
Abstract translation: 目的:建立施工工作计划后,根据工作规划,提供绩效评估体系,管理必要资源配送信息,防止材料流失。 构成:运营商服务器(10)处理关于参与者终端(40)的用户认证。 运营商服务器通过参与者终端提供的分发信息来分析资源的提供性能。 操作员服务器将分析的资源供应性能信息存储到DB服务器(20)。 操作服务器通过计算可靠性,有用性,相关工作效率来分析工作绩效。
-
-
-
-